|
4.) ASSESSMENT OF EIA PRACTICE BEYOND LAW
The laws presented so far provide the legal basis for EIAs. However, as
already demonstrated and as I will discuss in further detail in chapter 5, the
legal conditions grant a great deal of discretion and thresholds within which
project owners, authorities and other persons involved can act. In practice,
divergences of EIA procedures among member states might be greater or smaller
than it is provided for by the relevant laws. These practical aspects will be
briefly assessed in this chapter, by comparing two indicators for them: (1) The
typical duration of an EIA and (2) the views of stakeholders on the application
of screening criteria.
4.1. Duration of EIA
The duration of the EIA proceedings are a crucial factor for the costs
involved: The more concise the proceeding between the submission of the EIS on
behalf of the project owner and the publication of the final decision, the more
cost-effective it is. I therefore thought that a comparative assessment of
proceedings duration would be an interesting index to evaluate, after having
read such a study on EIAs in Austria and Liechtenstein. However, I found only
insufficient data for Germany and the UK; even the Austrian studies turned out
to have their limitations.
In Germany, the EIA practice diverges very much from Land to Land (Ref. 70).
Proceeding durations in general have been criticised for being too long and too
elaborate. In general, delays occur most commonly due to insufficient
information provided by the project owner (Ref. 68, Ref. 69). The EIA in Germany
is not an independent proceeding (as demonstrated in chapter 2), but done within
the general framework of another clearance proceeding
(„…Bundesimmissionsschutzgesetz-Genehmigungsverfahrens, eines
Planfeststellungsverfahrens nach Verwaltungsverfahrensgesetz (VwVfG) oder eines
Genehmigungsverfahrens nach Wasserhaushaltsgesetz, Erlaubnis gemäß § 7 WHG,
Bewilligung gemäß § 8 WHG“ Ref. 70). Accordingly, the length of the EIA is
determined by the other proceeding. Neither proceedings under the
Wasserhaushaltsgesetz (“water consumption law”) nor under the
Verwaltungsverfahrensgesetz have deadlines or time limits (Ref. 70).
In Austria, the length of EIAs has been subject to assessments twice (see Ref.
68 for a study from 2006 using data from 2000; and Ref. 71 for a study from 2009
with more current data). In Austria, proceedings are also often criticised for
being too slow, which was the reason for the evaluations. The first study of
2006 was dismissed by environmental organisations for the small sample size it
had used.
The 2009 study evaluated EIAs that were done between 01-01-2005 and 01-03-2009.
It used a representative sample and showed a median length for the proceeding of
380 days. However, the data used for this evaluation was rather thin. The
average would have included exceptionally long EIAs, which would have amounted
to 452 days. A division of the data into sectors showed that mining projects
were the most demanding ones, with an median length of the EIA of 600 days;
water management project were those with the lowest median length of only 293
days. The former case was based on the evaluation of five EIAs, the latter of
only four; it is therefore fair to doubt this study.
However, the older assessment of 2006 showed similar trends of 400 days on
average for a regular EIA and a median of 380 days (Ref. 68). It is worth noting
that the found actual length of EIAs goes beyond what the laws aim for: “Es kann
in diesem Zusammenhang allerdings nicht unerwähnt bleiben, dass die
ambitionierten Entscheidungsfristen des §7 UVP-G 2000 von 9 Monaten für
UVP-Verfahren und 6 Monaten für vereinfachte Verfahren noch nicht ganz erreicht
werden“ (Ref. 68). This still applies according to the 2009 study.
For the United Kingdom, no equivalent study or relevant information was found.
In this context, it is worth noting that there is a high degree of fragmentation
in EIA practice as a result of the geographic and sectoral sub-division of
relevant legislation (as shown in chapter 2). Due to this, framework conditions
for EIAs can diverge significantly within the UK and make a study on EIA
practice difficult and complex. It might well be that for this reason, no such
study has been done so far. However, at least the official guide to the EIA for
developers re-iterates the legal commitments for the authorities: “The planning
authority is required to determine a planning application which is the subject
of environmental impact assessment within 16 weeks from the date of receipt of
the environmental statement, unless the developer agrees to a longer period”
(Ref. 56).
4.2. Stakeholder views on screening practice
As I will discuss in further detail in chapter 5, there are very few
comparative studies done on EIA practice in the EU. The most extensive one was
published in 2009 and dealt only with a selected range of issues, including the
screening practice (Ref. 4). This so-called “(IMP)3” survey supplemented a
report by the commission to the council that investigated the legal aspects of
EIA implementation (Ref. 72). Both documents were published around the same
time.
The (IMP)3 report (Ref. 4), from which the following paragraphs draw their
information, was based on an extensive survey among 183 EIA stakeholders and 53
additional interviews. The data collected this way provided me with a unique
opportunity to get a direct view on EIA practice. One question of the survey
dealt with the projects that are subject to the EIA (thus screening). The study
reports that most of the stakeholders were generally satisfied regarding three
aspects explicitly investigated: (1) The list of projects that are subject to an
EIA; (2) the screening systems that are applied; and (3) the description of the
projects and the applied thresholds.
Some problem areas that were identified in the EIA directive’s annexes
contradict these findings. The survey showed three key issues: (1) A lack of
accuracy in the interpretation of screening criteria; (2) a lack of evidence for
matching screening criteria with potential impacts; (3) a need for tighter
guidelines and more research on screening practice. Furthermore, a few project
types were suggested for inclusion in annex I, alongside with minor adjustments
of criteria or thresholds in already included project types. There is a
recurring result of two responses that contradict each other. For example, “an
almost equal proportion of stakeholders responded that there were too many
project types as too few” (Ref. 4). This allows three possible conclusions:
Either the stakeholders perceive the situation very much based on their
background; or the situation among member states diverges strongly; or the data
is insufficient for drawing general conclusions (in this context, note the small
sample size of stakeholders per member state). Along this observation, the
authors recommend further research into problems with screening, in particular
project descriptions.
Nevertheless, one can find some general conclusions in the report: “There is a
great deal of variation among the levels to which some of the thresholds are set.
This is very likely regional or nationally dependent, and dependent upon
experience of those stakeholders working in those areas” (Ref. 4). An
interesting suggestion was derived from a survey on merging the two annexes of
the EIA directive into one: Some respondents suggested to instead link EIA
obligations to environmental impacts rather than project features; this way,
features that are specific for the region or project site could be taken into
account in a more standardised fashion.
On the level of individual member states, the survey also assessed the data for
particularly interesting replies and presented them according to MS and type of
stakeholder. The answers of the participants from Germany, Austria and the
United Kingdom are shown in fig. 4.1, fig. 4.2 and fig. 4.3 below. Like all
other results, they will be discussed in chapter 5.
Figures excluded
Fig. 4.1: Results of a survey on screening practice. Selected suggestions for
improvement according to member states and stakeholder (simplified from Ref. 4).
Fig. 4.2: Results of a survey on screening practice. Selected suggestions for
improvement according to member states and stakeholder (simplified from Ref. 4).
Fig. 4.3: Results of a survey on screening practice. Selected suggestions for
improvement according to member states and stakeholder (simplified from Ref. 4).
return to "CV
(English)" or "Lebenslauf (Deutsch)"
|